Mun Fong CHAN陳滿鋒 Adjunct Professor |
Academic Qualification
Virginia Polytechnic Institute & State University, USA | ||
Civil Engineering, Structural Division | ||
1985 | Ph.D. Degree | |
University of California, Berkeley, USA | ||
Structural Engineering & Structural Mechanics | ||
1982 | M.Sc. Degree | |
1981 | B.Sc. Degree |
Work Experience
1999 -Present | CIVIL Engineering Consultants Company Limited | |
Director | ||
1997-99 | San Wa Bao Civil Engineering Co., Ltd. | |
Chief Engineer | ||
1988-97 | Laboratório de Engenharia Civil de Macau (LECM) | |
Department of Buildings and Structures | ||
Since 1992 — Department Head | ||
1990 – 1992 — Division Head | ||
1988 – 1990 — Civil Engineer |
Teaching Experience
2013-15 (Part-time) |
University of Macau Faculty of Science & Technology Lecturer |
|
1989-92 (Part-time) |
University of Macau Faculty of Science & Technology Assistant Professor |
|
1988-89 | University of East Asia Installation Committee of Engineering Program Committee Member |
|
1986-88 | University of East Asia Junior College Lecturer |
Research
Research Interests
- Piling in Macau soil conditions.
- Pile soil-structure interaction and its effects on earthquake analysis of structures in Macau.
- Analysis and restoration techniques of historic buildings in Macau.
Major Projects Involved
From 2016 | Cape Verde Intergrated Resort & Casino Project, Cape Verde | ||
• | To carry out structural design review on Client’s behalf. | ||
2017-19 | Social Facility Fit out Project inside Public Housing at L$ & L5 in Fai Chi Kei, Macau | ||
• | To review and coordinate structural and plumbing & drainage design. | ||
2013-16 | Macau Fisherman’s Wharf – Phase I Extension | ||
• | To serve as Project Manager for the planning and development of the project. | ||
2011-13 | Macau Light Rapid Transit Phase 1 Segment C250 | ||
• | To serve as Coordinator of design team in this comprehensive design of a 2km viaduct and 4 stations. Team contains consultants from Hong Kong and Macau. | ||
2010-11 | Public Housing in Fai Chi Kei | ||
• | To serve as the Registered Engineer of the project. | ||
New Town E1 Reclamation Area and Seawall Construction | |||
• | To carry out reclamation design of the project. | ||
CN3 in Seac Pai Van | |||
• | To serve as the Registered Engineer of the project. | ||
Cotai Fire Station | |||
• | To serve as the Registered Engineer of the project. | ||
2008-09 | Coloane Venetian Expo Center | ||
• | To serve as Independent Checking Engineer for Sun Fook Kong – Kun Fai Engineering and Construction Co. Ltd. | ||
City of Dreams at Cotai | |||
• | To serve as Independent Checking Engineer for Leighton/China State/John Holland Joint Venture. | ||
2008 | Wynn Resort Macau | ||
• | To serve as Independent Checking Engineer for Leighton/ China State Joint Venture in a 90m high casino-hotel complex. | ||
• | To review and sign off temp work design including steel structure shop drawings and curtain wall design. | ||
2007 | Hotel Lisboa Third Entrance Renovation Work | ||
• | To serve as the Registered Engineer of the project. | ||
2006-07 | Walkway Along Main Reservoir | ||
• | To lead site inspection & management team. | ||
2004-06 | Starworld Casino & Hotel Macau | ||
• | To serve as Registered Engineer to sign foundation design, excavation and lateral support design, and structural design by Meinhardt, HK. in a 135m high casino–hotel complex. | ||
• | To advise Meinhardt on local design codes and regulations. | ||
2001-05 | Volcano Structure, Macau Fisherman’s Wharf | ||
• | To serve as Registered Engineer to sign structural steel skeleton of volcano design by Sanderson Group Pty. Ltd of Australia. | ||
• | To advise Sanderson on local design codes and regulations. | ||
• | To review and sign off construction drawing by Sanderson. | ||
Macau Fisherman’s Wharf – Phase I | |||
• | To serve as the “Technical Director” of the work. | ||
• | To review design, construction methods, procedures, and schedules submitted by the contractor. | ||
• | To lead engineering design team including E&M deisgn. | ||
Goddess A-Ma Cultural Complex | |||
• | To lead engineering design team including E&M deisgn. | ||
• | To coordinate among specialized design teams including cable car design. | ||
2003 | Macau Landmark Platform | ||
• | To coordinate structural design and work license application. | ||
• | To liaise with Fire Department on emergency escape issue. | ||
2001 | New Road in Main Resevoir | ||
• | To lead construction management team. | ||
1997-99 | China Ministry of Foreign Affairs Building in Macau | ||
• | To represent the Owner (China Ministry of Foreign Affairs) as the “Técnico Responsável” of the work. | ||
• | To review design, construction methods, procedures, and schedules submitted by the contractor. | ||
• | To chair site meetings to ensure proper executions of approved construction methods and procedures. | ||
• | To coordinate among specialized design teams. | ||
1997-99 | Reservoir T-50 in Taipa | ||
• | To review the structural design and constructiveness of this 20,00m3 capacity reservoir located in Taipa hill. | ||
• | To modify structural design as needed after the review. | ||
• | To represent the Owner (The Macao Water Supply Co. Ltd.) as the “Técnico Responsável” of the work. | ||
1998 | Land Reclamation for Future Taipa Hospital | ||
• | To carry out reclamation design of this 93,000m2 land including monitoring scheme for settlement during construction. | ||
• | To provide technical guidance and support to construction team during work. | ||
1993-97 | Protocolo de Cooperação, established between Direcção dos Serviços de Solos, Obras Públicas e Transportes (DSSOPT) and LECM | ||
• | To implement quality control systems and to supervise their execution on site in various DSSOPT projects including: — Edifício dos Gabinetes dos Secretários Adjuntos — Silo Automóvel junto à ETAR (Public Car Park) — New Macau Observatory in Taipa — Viaducts between NAPE and ZAPE — Complexo Desportivo da Taipa (Macau Stadium) — New Fire Fighting Department Headquarter |
||
• | To prepare and to edit new regulations and norms in different areas of civil construction including: — Regulamento de Segurança e Acções — Regulamento de Estruturas de Betão Armado e Pré-esforçado — Regulamento do Betões — Norma de Aço para Armaduras Ordinárias — Norma de Cimentos |
||
Since 1990 | New Macau-Taipa Bridge | ||
• | To implement Q.C. plan on precast and prestressed concrete structural elements such as piles, slabs, columns, beams, and girders for cable-stayed spans. | ||
• | To modify and execute instrumentation and monitoring program of the bridge. The plan involves measuring of strains, displacements, and rotations of different structural elements at various stages of their construction including at services. | ||
Since 1989 | Macau International Airport Construction | ||
• | To study and compare the various construction alternatives for the airport in the planning phase. | ||
• | To prepare quality control scheme and quality control manual in the construction phase. The Q.C. scheme covers R/C structures, prestressed structures, and steel structures for runway, taxiways and all facilities buildings in the terminal area. | ||
• | To lead teams for the execution of the above Q.C. work. | ||
Since 1989 | To plan and to carry out structural evaluation on existing structures and to prepare rehabilitation/repair/strengthening schemes. Examples of such works include | ||
• | Ponte General Nobre de Carvalho | ||
• | Igreja de S. Domingos | ||
• | Seminário de S. José | ||
• | Mercado de S. Lourenço | ||
• | Reservatório da Flora | ||
• | Edifício do Banco Weng Hang | ||
• | Campanário do Edifício Sede dos Correios de Macau | ||
1993 | Teledifusão de Macau Transmission Tower | ||
• | To plan and perform complete inspection on deterioration due to rusting of the 75 meter steel frame. Specifications on repair method were prepared based on findings from the inspection. | ||
1991-92 | Nova Creche Building | ||
• | To represent owner as project manager for construction of the 6-stories delux building. | ||
1990-92 | Tunel de Guia and Viaduto de San Francisco | ||
• | To provide Q.C. on all reinforced and prestressed concrete components of the structures. Exerting tight cooperation with the construction team, the project for the 400 m long viaduct was completed in 4 months in order to allow traffic for the Macau Grand Prix Auto Racing. | ||
1989 | New Macau Jetfoil Terminal | ||
• | To perform structural analyses and designs for the R/C structures and steel frames of the 3-stories complex. | ||
1989 | Tong Lei Concrete Factory Buildings | ||
• | To perform complete R/C analysis and design for the various facilities of the factory including foundation and retaining walls. |
Other Trainings
- 36 Hours Training Course on “Building Information Modeling (BIM)” offered by Macau Productivity and Technology Transfer Center and University of Science and Technology Macau, Nov. 2016 to Jan. 2017.
- Workshop on “Green Management Series: Carbon Audit” offered by Macau Productivity and Technology Transfer Center and Gabinete para o Desenvolvimento do Sector Energético, October 2010.
- Workshop on “Analysis and Design of Tall Building Structures” offered by The Hong Kong University of Science and Technology, October 2001.
- Workshop on “Wind Effects on Buildings and Structures” offered by The Hong Kong University of Science and Technolopy, September 1999.
- Workshop on “Repair and Reinforcement of Damaged and Aging Concrete Structures using Advanced Composite Materials” offered by The Hong Kong University of Science and Technology, October 1998.
- Short Course on “ISO/IEC Guide 25 Quality System in Test Laboratories” offered by Laboratório de Engenharia Civil de Macau and National Civil Engineering Laboratory of Portugual, February 1997.
Publications
- Chan, M. and Lam, H., “Stiffening of Concrete Beams by Plate Bonding”, Report 1106, Laboratório de Engenharia Civil de Macau, 1997.
- Chan, M. and Cheong, K., “Static Loading Test on Viaduto de Acesso Norte ao Túnel da Guia”, Macau Engineering Bulletin, Vol. 3, Oct., 1996.
- Catarino, J. and Chan, M., “Long Term Behaviour of the New Macau-Taipa Bridge – Analysis and Observation of Creep and Shrinkage Effects”, keynote paper in the Fifth Conference on Education, Practice and Promotion of Computational Methods in Engineering Using Small Computers, Macau, August, 1995.
- Chan, M., “Building After a Fire – Reconstruction or Rehabilitation?”, Macau Engineering Bulletin, Vol. 1, July, 1995.
- Chan, M., “Potential Use of Municipal Solid Waste Fly Ash in Concrete”, Boletim do Laboratório de Engenharia Civil de Macau, May, No. 11, 1993.
- Chan, M., “Statistical Analysis on Tensile Testing Results of Reinforcing Steel Bars Used in Macau”, Boletim do Laboratório de Engenharia Civil de Macau, September, No. 9, 1992.
- Ao, P. and Chan, M., “An Introduction of Cone Penetration Test and Its Applications in Macau International Airport Project”, Macau Institute of Engineers Annual, 1989.
- Chan, M. and Barker, R., “Sheet Pile Interlock Behavior: A Moving Contact Problem”, Proceedings of the Ninth Conference on Electronic Computation, Birmingham, Feb., 1986.
- Chan, M. and Barker, R., “Finite Element Studies of Sheet Pile Interlock Connection”, Final Report, Task 1.4, 1.5, prepared under Contract No. DACW 39-84 c-0031 for Department of the Army, Waterways Experiment Station, Corps of Engineers, 1985.
Professional Affiliations
- The Royal Institute of Chartered Surveryors, Fellow Member 2016
- Chartered Institution of Civil Engineering Surveyors, Fellow, 2016
- 中國土木工程學會會員
- 澳門工程顧問商會上任會長
- 澳門工程師學會監事會成員
- 澳門岩土工程協會會員
- 澳門金屬結構協會會員
- 澳門建築機械工程商會會員
- 澳門土木及結構工程師學會會員
- 澳門建造商會會員
- 澳門科學協進會會員
- 2017-2019澳門體育委員會委員
- 2015-2019澳門建築、工程及城市規劃專業委員會委員(代任人)
- 2005-2015澳門舊區重整諮詢委員會可持續發展小組委員
- 2003-2015澳門財政局房屋估價常設委員
Contact Details
Faculty of Science and Technology
University of Macau, E11
Avenida da Universidade, Taipa,
Macau, China
Email: munphie@gmail.com